A detailed examination of the geological risks involved in the project, including tunneling through fault zones and the excavation of massive underground caverns.
InfrastructureRenewable energyDennis BarnesHon Sarah HendersonSenate Environment and Communications Legislation CommitteeSupplementary Budget Estimates 2026–27Senate Environment and Communications Legislation Committee, 26 Oct 202631520
Transcript
Hon Sarah Henderson
>> mean, isn't it the case that thegeotechnicalchallenges are so complex that there isstill significant risk in relation tocompletion of this project?
Dennis Barnes
>> Yeah. So, I I'll probably refer to twothings. I think uh 3 years ago I wouldhave been sat here when the powerstation complex was hardly started andwe would have said once the cavern isexcavatedby about a third we would have gottenover a major geological risk. The cavernis now 90% excavated. So that geologicalrisk we're concerned about didn'tUh two years ago we got seriouslyconcerned about this long plane faultzone. Uh and that drove us to acquire afourth tunnel boring machine and put inplace, you know, specific technology tocover that zone. So yes,you're digging 40 kilometers of tunnelsin a mountain and building two cavernsthe size of the Sydney Opera House.Geological risk is a feature of this