Senator McGrath questions the department on the construction schedule for the Circular Quay renewal program and the impact of PII claims on information disclosure regarding project timelines.
Speakers: Hon James McGrath, Lok Potticary, Jessica Hall
InfrastructureProcurementHon James McGrathLok PotticaryJessica HallSenate Rural and Regional Affairs and Transport Legislation CommitteeSupplementary Budget Estimates 2026–27Senate Rural and Regional Affairs and Transport Legislation Committee, 26 Oct 202618931
Transcript
Hon James McGrath
>> The Commonwealth's infrastructureinvestment program websitelists the timetable for the circular keyrenewal program as TBC.The initial infrastructure Australiabusiness case evaluation said theproject was to commence in 20uh 25 and finish by 2028.What is the current what is thedepartment's current understanding ofwhen construction will commence and be
Lok Potticary
So, Senator, um, as part of arequest for documents, the minister hasmade a public interest immunity claimover a number of, uh, documents relatedto this project. So, um, I think I'mgoing to have to take on notice yourquestions given that the minister's madepublic interest immunity claim, and Ijust want to be able to check thosebefore responding.
Hon James McGrath
>> I I'm not asking for documents here. I'masking um what is the departdepartment's current understanding ofwhen construction will commence and becompleted. So I'm I'm I'm not asking fordocuments. I'm just askingthat that question with the twocomponents to it.
Lok Potticary
>> I don't have a time frame for you,
Hon James McGrath
>> When when you say you don't have thetime frame, does anyone in thedepartment have the the time frame?
Lok Potticary
I really would like to take given thatthe minister has made a public interestimmunity claim over documents. I wouldlike to take it on notice and be able toconsult with responding to yourquestions around this project. Senator,
Hon James McGrath
in relation to the question that I'vewhich I I would have thought is a prettyeasy question in a way. Um, and I I'llrepeat it because the website lists thetimetable for the circular key renewalprogram as TBC.The original sorry the initialinfrastructure Australia business casesaid the project was to commence lastyear in 2025 and finish by 2028.The question I'm asking is what is thedepartment's current understanding ofwhen construction will commence and be
Jessica Hall
completed? So, Senator, we haven'tfinalized with transport for New SouthWales at this stage the start and um enddates with transport for New SouthWales. We're still confirming the costand scope of the works to be undertaken.