The department explains the decision to move grant assessments from a multi-party parliamentary panel to internal departmental staff to improve efficiency. Additionally, the minimum grant amount was reduced to $250,000 to increase eligibility, and an update is provided on the completion status of Round 1 projects.
Speakers: Hon James McGrath, Lisa Rauter, Unknown Speaker, Jessica Hall, Speaker 36, Senator Glenn Sterle
Grants administrationIntegrityHon James McGrathLisa RauterUnknown SpeakerJessica HallSpeaker 36Senator Glenn SterleSenate Rural and Regional Affairs and Transport Legislation CommitteeSupplementary Budget Estimates 2026–27Senate Rural and Regional Affairs and Transport Legislation Committee, 26 Oct 202633936
Transcript
Hon James McGrath
now uh the government refused to complywith an order production documents thatI actually lodged seeking clarity on thedecision-making processes of themulti-party parl parliamentary panelwhich assessed the last round of grantsin her response to the IBT the ministerum the and I quote the Albanesegovernment is committed to transparencyin the delivering programs.Uh I'm not sure that's entirelytruthful.Um the minister went on to say that theopen and competitive assessment proassessment process was aided by therecommendations of the multi-partyparliamentary panel. So my question ishas a decision been made yet aboutwhether next funding round will beassessed by a multi-party parliamentarypanel um in May the evidence was thatyou didn't think that process would beused again.
Lisa Rauter
That's correct, Senator. So, theassessments will be done by departmentalstaff.
Hon James McGrath
has it why can I ask why was the shiftfrom the parliamentary panel todepartmental staff?
Lisa Rauter
>> Uh, look, it's a decision of governmentas to how the program is administered.Um, we also have an exemption for thosefor throwing growing regions andthriving suburbs and the business grantshub which means all of theadministration now happens within thedepartment. Um and it made sense forthose assessments uh to be made insidethe department as well. Uh and we foundthat that perhaps would be moreefficient and timely.
Hon James McGrath
>> Was was there a um a formal evaluationor a feedback process in relation to thethe process that the multi-multi-arty parliamentary panel uh wentthrough?
Lisa Rauter
>> Not that I'm aware of, but I wasn'tresponsible for the program at the timethat we used a multi-party panel.
Hon James McGrath
>> If you just take that aspect on onnotice, that's possible, please. Thankuh the forecast funding opportunitystates that the minimum grant amount hasbeen reduced from 500,000 to $250,000.>> Um what was the basis for that change tothe eligib eligibility to those
Lisa Rauter
requirements? It was just to enable moreprojects to be eligible under the
Hon James McGrath
>> Of the 70 projects approvedunder round one in December 2024,>> y>> how many as at um so now but um havestarted um have been delayed havereached practical completion.
Jessica Hall
Senator, I believe a lot of thatinformation is in the Cadell table thatwas actually um uh tabled earlier today.
Speaker 36
>> Okay. I can say it's at 31 August. Threeprojects were completed.
Hon James McGrath
>> Three projects.>> Y that's been tabled earlier. I willlook at um Senator Cadell's umpaperwork. Can I move on? Thank you forthat by the way. I appreciate that.
Senator Glenn Sterle
>> Just let you know we got two moreminutes before the break.