Speakers: Hon Bridget McKenzie, Mr. Jim Betts, Senator Glenn Sterle, Speaker 15, Paula Stagg, Rachel Parry, Senator Ross Cadell

Transcript

Paula Stagg

>> Uh so we are working with uh CSRO around a uh a green fuel strategy. So we are currently in negotiations on delivery of

Hon Bridget McKenzie

>> So none of the funds have been expended.

Paula Stagg

>> Not yet Senator.

Hon Bridget McKenzie

>> Okay. Um I do thanks to my team watching on at home. My understanding is in the budget the $100.1 million uh of of the government's energy sovereignty, fuel security and resilience program was actually not allocated to Arena. It was to allocated to the department. Sorry, Miss Parry.

Rachel Parry

the 1.1 [clears throat] billion cleaner fuels program is is allocated to Arena is the delivery agency for that program.

Hon Bridget McKenzie

>> I've got budget paper number two and if it's a $100.1 million was allocated to infrastructure get my team. Can you send me the page number please? Um all right transport and infrastructure just stay at the table if you know the answer to that. Sorry, somebody does. Somebody's come >> Page 35, budget paper two.

Paula Stagg

that up right now. I don't, it doesn't

Senator Ross Cadell

sound like it's related. Sorry, Bren

Paula Stagg

Brennon Buckley, assistant secretary. It

Senator Ross Cadell

doesn't sound like it's related to the cleaner fuels program, but I'll just

Hon Bridget McKenzie

>> Thanks, mate. Appreciate it. What I was wanting was the fuel security and resilience, the energy sovereignty piece. Um, I've just got some questions on the net zero road map and action plan. Um, have all the $7.8 million commitment from the 2324 budget being expended on delivering the net zero road map and action plan.

Paula Stagg

>> Uh, Senator, I might need to refer to my colleagues uh in uh the corporate division that had oversight of that at the time.

Hon Bridget McKenzie

>> Well, that's why we're doing this in

Mr. Jim Betts

corporate. My understanding is that was a terminating measure which is now terminated with the release of the action plan in September

Hon Bridget McKenzie

>> right

Mr. Jim Betts

>> 2024.

Hon Bridget McKenzie

>> So how much were of the 7.8 was actually expended and how much remained back into consolidated revenue.

Mr. Jim Betts

>> We'll get that information for you.

Hon Bridget McKenzie

>> Is anyone in corporate here?

Mr. Jim Betts

>> We will find rather than waste your time. Why don't we just find out the information?

Hon Bridget McKenzie

>> I've got lots of these. We're going to go down keep the list and >> let's keep the list. Um in terms of the IIP headroom, so this isn't a question for IIP. Please stay corporate at the table. Um there is almost 11 billion unallocated headroom within the IIP at the time of the budget attributed to the 203536 year. Has any of that funding been committed since the budget?

Mr. Jim Betts

>> We will need our infrastructure colleagues at the table for

Hon Bridget McKenzie

>> Could the new arrivals are they able to tell me about the $7.8 8 million from the 2324 budget, whether that's been expended, if how much was left over in the net zero road map and action plan.

Senator Glenn Sterle

>> Is that because the people who need have could have the answer are not here yet?

Hon Bridget McKenzie

No, it's not. This was supposed to be incorporated.

Senator Glenn Sterle

>> I'm just I'm just asking because I'm just trying to get I I had a question for you. Sorry.

Speaker 15

is um we don't necessarily come up with every single line item that the

Senator Glenn Sterle

department spends money on. So, we need to go back into the system. I'm just trying to establish because if the people that if if I know you're saying corporate Senator, but I know you don't want to lose the people cuz when you get to outcome too and you find out it was

Hon Bridget McKenzie

corporate very helpful with the previous um official said, "Well, I'll need my friends from corporate to help me answer."

Senator Glenn Sterle

>> Would it assist if you just rattle through your questions and if you haven't got them and if it's in a different outcome, just let us know.

Hon Bridget McKenzie

>> Yeah. No one said it's in a different

Senator Glenn Sterle

outcome. No, because I'm seeing a lot of musical chairs and Mr. Betts did hint that um your questions could be in the other outcome. I'm just trying to assist the process. I'll sit I'm sitting at 11:00. I'm not going anywhere. So, I'm not worried about that.

Mr. Jim Betts

>> So, on the net zero road map, I will get my people to confirm this, but that was a terminating measure y >> for the production of a strategy, a road map document which was completed and published um in 2025 from memory. So my guess is that that money was fully expend extend expended um and certainly um that um measure has been completed. Whether there was a small balance of funds left at the end of that we will

Speaker 15

>> Yes. So the information I have and we uh actually I believe tabled this as part of our response to Senator Cadell's request uh which outlined the funding for the net zero assessment roadmap and action plan. Uh and uh the secretary is correct. It was a terminating measure. So no funding uh available this financial year. Uh and um as it was departmental money that money has been uh fully allocated and spent in prior

Hon Bridget McKenzie

>> on the actual um matter it was meant to be or did you reallocate

Mr. Jim Betts

>> that document is in the public domain?

Hon Bridget McKenzie

>> No no I appreciate that. My question is did it cost $7.8 million?

Speaker 15

>> Well I will confirm that as I'll take that on notice and come back to you with involve delivering of uh the road map and action plan and obviously funding of the staff that were associated with that

Hon Bridget McKenzie

>> Right. Um is it the government's intention to retain the high-speed rail authority beyond June 2028?